Can a pool be renovated without rebuilding it?

Yes. If the concrete structure is sound, the old finish is removed, the surface is prepared and the quartz aggregate finish is applied over the shell. There is no demolition and no digging: you replace the skin of the pool, not the pool. The result is a new finish with no joints, a sandy feel and the water colour the quartz gives.

When it is time to renovate

Some signs cannot be fixed with a patch, because they come back every season:

Can you put a new finish over tiles?

Not over the tiles as they are. Loose pieces and any finish that is not firm are removed, and the surface is left clean and sound. Then the Bond-Tite bonding coat is applied, which is what makes the new finish grip the old shell. The same goes for paint: it is removed completely before starting.

That is why surface preparation is the biggest part of a renovation, and the part that decides whether the finish lasts. It is done by trained crews, who assess each shell before starting.

Preparing a pool shell before applying the finish
Preparing the shell before applying: the part you do not see, and the one that decides the result.

A renovation, step by step

  1. Assessment from photos. You send us photos and dimensions, we check the state of the shell and tell you what it needs.
  2. Surface preparation. Loose pieces and any finish that is not firm are removed, paint is stripped and the surface is cleaned. How long it takes depends on the state of the pool.
  3. Bond-Tite bonding coat. Applied over the prepared surface and left to dry for 24 hours before the finish.
  4. Applying the finish. Three days on average, with the quartz aggregate sprayed and trowelled on site.
  5. Filling. The pool is filled after 48 hours, not weeks.

How long does it take to renovate a pool?

The finish takes three days on average to apply and the pool is filled after 48 hours. On top of that comes surface preparation, which depends on the state of the shell, and 24 hours for the bonding coat to dry. From the photos we can give you the timing for your pool.

What time of year can a pool be renovated?

Whenever the temperature is between 10 and 38 °C and it is not raining. The best time is spring or autumn: the work is done without losing the summer and the pool is ready for the season.

Renovate in spring and the pool is finished by June. Leave it until June and you risk spending part of the summer with the pool under works.

Is it worth it compared with new tiles or a new liner?

Retiling means joints that come loose again and regrouting every few years; a new liner means replacing it again in 10–12 years. Quartz aggregate bonds with the concrete and, once applied, does not call for building work again. It is also cheaper than mosaic tile of comparable quality.

And you gain what the old pool did not have: a Class 3 slip-resistant surface, warmer water because the aggregate stores heat, and a look that changes the whole property. It works for private pools, communal pools, hotels and municipal pools.

Applying a quartz aggregate finish to a curved pool
Applying the finish to a curved pool.

About the quartz finish · See our projects

Tell us about your pool

Send us the dimensions and a few photos and we will reply with a material and lead time estimate within one working day, no strings attached.